Top plate and bottom plate
Studs go straight down
Nogs/dwang horizontal though gaps in studs to holed in place and for support.
Individual measurements
Running measurements
Over all measurements
Thursday, 17 May 2012
piles
Complete pile task analisusis sheet
Calculate pile quantities
Set out piles
Instal bearers
H5 radiata 125mm x 125mm
Ordinary pile 300mm deep
Anchor pile 900mm deep
Embedded in concrete
Structural vertical member designed to support the bearers and to transfer vertical and horizontal loads down to the group.
Bearer:
Structural horizontal beam supports joints and transfer loads from above down to the piles
Calculate pile quantities
Set out piles
Instal bearers
H5 radiata 125mm x 125mm
Ordinary pile 300mm deep
Anchor pile 900mm deep
Embedded in concrete
Structural vertical member designed to support the bearers and to transfer vertical and horizontal loads down to the group.
Bearer:
Structural horizontal beam supports joints and transfer loads from above down to the piles
thurz 17th work ex
At work experience today we used a digger to dig 3 holes that were 2.2
meters deep and then craned in 3 poles that were 280 mm diameter s e d
poles for the support of a hay shed. When we were craning them in we
used a string line off the corner post that was already in to get the
exact depth the poles needed to be. Then we used sol plates to hold the
poles steady while we braced them up using spear timber a nail gun pegs
sledgy and a straight edge spirit level. Tomorrow we are going to poor 1
meter of concrete in each hole to support the poles so the don't sink
and to make them permanent. Then once the concrete is in we will fill
the rest of the hole with dirt and the start building the roof